Project Description:
WESTHAMPTON- BRIDGE REPLACEMENT, W-27-015, NORTH ROAD OVER ROBERTS MEADOW BROOK
'The proposed work includes replacing the bridge carrying the North Road bridge over Meadow Brook in Westhampton. The proposed bridge will be 24.0 feet curb to curb with no sidewalks. The bridge will be closed to vehicular and pedestrian traffic in construction. A detour will be provided.
Location:
  • Town of Westhampton
  • Resident Engineer: Thomas Doody
    Construction Contract Value: $772,349.00
    Construction Bid Price: $699,826.37
    Initial Construction Estimate: $780,541.80
    District: District 2

    Contracts (6) Progress
    # 34490 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 5 - Contract A Final
    # 57735 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64324 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 65756 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final
    # 79519 -- Construction Contract
    Bridge Replacement (W-27-015) (Concrete) - North Road over the Roberts Meadow Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 10/06/2007
    Project Status Advertised 08/31/2013
    Project Management
    100% Design 100% Package Received 05/01/2013
    100% Design 100% Package Comments to DE 05/31/2013
    25% Design 25% Package Received 05/30/2007
    25% Design 25% Package Received 10/15/2010
    25% Design 25% Package Received 11/13/2012
    25% Design 25% Package Comments to DE 12/11/2012
    25% Design 25% Package Comments to DE 12/11/2012
    25% Design Design Public Hearing 02/12/2013
    75% Design 75% Package Received 05/01/2013
    Final Design PS&E Received 06/25/2013
    Final Design PS&E to FAPRO 08/28/2013