Project Description: |
NORTH ADAMS- CONSTRUCTION OF CHEMICAL STORAGE SHED ON ROUTE 8A
|
Location: |
|
Resident Engineer: | Amer Raza |
Construction Contract Value: | $254,140.00 |
Construction Bid Price: | $254,040.00 |
Initial Construction Estimate: | $210,490.00 |
District: | District 1 |
Current Status: | Shed is about 95% complete. Contractor is installing door and electrical service. (as of 11/28/2006) |
|
Bridges |
|
|
|
|