Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 2- WINDOW AND DOOR REPLACEMENT AND OTHER MISCELLANEOUS WORK AT ADMINISTRATION BUILDING
Location:
  • City of Northampton
  • Resident Engineer: Perry Knickerbocker
    Construction Contract Value: $758,725.54
    Construction Bid Price: $758,725.54
    District: District 2

    Contracts (1) Progress
    # 52958 -- Construction Contract
    Window and door replacement and other work at the MHD District Office in Northampton Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/22/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 04/25/2005
    Project Status Initiated 11/16/2004
    Project Status Advertised 10/01/2005
    Project Management
    Final Design PS&E Received 09/19/2005
    Final Design PS&E to FAPRO 09/19/2005