TEMPLETON- BRIDGE REPLACEMENT, T-02-019, NORTH MAIN STREET OVER EAST TEMPLETON POND OUTLET
The purpose of the project is to replace the North Main Street Bridge over the East Templeton Pond Outlet. Stage construction will allow the bridge to remain open during construction with the use of a temporary signal. A new roadway surface and a sidewalk will be added.
Location:
  • Town of Templeton
  • Resident Engineer: Matthew Minihan
    Construction Contract Value: $981,201.00
    Construction Bid Price: $862,500.93
    Initial Construction Estimate: $1,100,553.00
    District: District 2

    Contracts (3) Progress
    # 57735 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68652 -- Construction Contract
    Bridge Superstructure Replacement (T-02-019) (Steel) - North Main Street over the East Templeton Pond Outlet. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/03/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 12/08/2004
    Project Status Advertised 04/16/2011
    Project Management
    100% Design 100% Package Received 11/19/2010
    100% Design 100% Package Comments to DE 01/10/2011
    25% Design 25% Package Received 03/21/2006
    25% Design 25% Package Comments to DE 08/20/2010
    25% Design Design Public Hearing 06/28/2007
    75% Design 75% Package Received 06/12/2009
    75% Design 75% Package Comments to DE 09/28/2009
    Final Design PS&E Received 03/21/2011
    Final Design PS&E to FAPRO 04/12/2011
    Consultant Contract Process NTP Issued 05/26/2005