Project Description: |
DEDHAM- NEEDHAM- WELLESLEY- WESTWOOD- RESURFACING AND RELATED WORK, I-95
|
Location: |
|
Resident Engineer: | James Slavit |
Construction Contract Value: | $4,128,504.00 |
Construction Bid Price: | $3,517,004.06 |
Initial Construction Estimate: | $3,288,886.00 |
District: | District 4 |
Current Status: | All roadway work and related items completed. Final inspection of traffic collection data stations forthcoming. (as of 11/09/2007) |
|
Bridges |
|
|
|
|