Project Description:
BARRE- RESURFACING & RELATED WORK ON ROUTE 122 (WEST STREET) INCLUDES ROUTE 62 (HUBBARDSTON ROAD)
This resurfacing project consists of 2" milling and resurfacing on a section Rte 122 and a section of Rte 62 in Barre. Section 1 is state-owned and begins just west of the intersection of Rte 122 and Pleasant St at mm 48.265 and proceeds westerly to the Barre/Petersham TL mm 52.074 for 3.809 miles. Section 2 is town owned and begins just east of the intersection of Rte 62 and Valley Rd mm 0.53 and proceeds easterly to the Hubbardston T L at mm 4.11 for 3.58 miles. Work includes new pavement markings, guardrail ends, repairing sidewalks and wheelchair ramps, and other incidental items.
Location:
  • Town of Barre
  • Resident Engineer: Stefan Toth
    Construction Contract Value: $2,099,458.00
    Construction Bid Price: $1,859,776.52
    Initial Construction Estimate: $2,294,404.00
    District: District 2

    Contracts (1) Progress
    # 58323 -- Construction Contract
    Resurfacing and Related Work on Sections Route 122 (West Street) and 62 (Hubbardston Road), (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/14/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 01/13/2005
    Project Status Advertised 03/28/2009
    Project Management
    75% Design 75% Package Received 01/30/2009
    75% Design 75% Package Comments to DE 02/27/2009
    Final Design PS&E Received 03/16/2009
    Final Design PS&E to FAPRO 03/18/2009