Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DUDLEY- FULL DEPTH PAVEMENT RECLAMATION ON ROUTE 31 (DRESSER HILL ROAD) FROM THE CHARLTON T.L. TO THE CONNECTICUT S.L.
Location:
  • Town of Dudley
  • Resident Engineer: Paul Thompson
    Construction Contract Value: $16,198,985.30
    Construction Bid Price: $2,119,615.70
    Initial Construction Estimate: $1,883,000.00
    District: District 3

    Contracts (1) Progress
    # 56305 -- Construction Contract
    This project consists of reclaiming and resurfacing Route 31 in Dudley. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/10/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/31/2005
    Project Status Initiated 01/18/2005
    Project Status Advertised 06/21/2008
    Project Management
    Final Design PS&E Received 09/05/2007
    Final Design PS&E to FAPRO 11/02/2007