Project Description:
QUINCY- WEYMOUTH- BRIDGE REPLACEMENT, Q-01-001=W-32-001, STATE ROUTE 3A (WASHINGTON STREET) OVER THE FORE RIVER
The proposed project includes the replacement of the Washington Street Bridge (State Route 3A) over the Fore River in Quincy and Weymouth. The new bridge will be a double leaf bascule or vertical lift bridge. The project also includes approach roadway work and possible intersection improvements/improved geometrics.
Location:
  • City of Quincy
  • Town of Weymouth
  • Resident Engineer: Kevin Laramee
    Construction Contract Value: $273,917,937.00
    Construction Bid Price: $244,622,670.00
    Initial Construction Estimate: $280,000,000.00
    District: District 6

    Contracts (9) Progress
    # 50281 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of the preparation of 25% plans,estimate,type study, sketch plans and permits for replacement of the Quincy-Weymouth Bridge. Final
    # 62936 -- Non-system contract type
    Statewide-Owner's Representative-Will perform peer reviews and manage cost recovery and value engineering on various projects.
    # 64303 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 65756 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final
    # 69762 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 71680 -- Construction Contract
    Bridge Replacement (Q-01-001=W-32-001) (Steel) (Fore River Bridge) - Route 3A (Washington Street) over the Fore River, (ABP) (DESIGN BUILD PROJECT) Completed
    # 76262 -- Non-system contract type
    Perform various assignments as the Owner's Representative for the peer review of engineering elements associated with satewide construction projects.
    # 77865 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77882 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/15/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 02/14/2005
    Project Status Advertised 05/22/2012
    Project Management
    100% Design 100% Package Received 03/27/2012
    25% Design 25% Package Received 12/19/2011
    Consultant Contract Process Scope to DE 02/01/2008
    Consultant Contract Process NTP Issued 10/29/2008
    Consultant Contract Process Workhours Approved 07/22/2008