Project Description: |
BOSTON- CONSTRUCTION OF TYPE II NOISE BARRIER , I-93 (SOUTHEAST EXPRESSWAY) AT SAVIN HILL AVENUE
|
Location: |
|
Resident Engineer: | Girard Allien |
Construction Contract Value: | $774,251.00 |
Construction Bid Price: | $563,410.00 |
Initial Construction Estimate: | $313,900.00 |
District: | District 4 |
Current Status: | This project is complete. Final inspection was held on 8/27/07. (as of 09/06/2007) |
|
Bridges |
|
|
|
|