Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- EMERGENCY AND NON-ROUTINE STRUCTURAL REPAIRS TO VARIOUS BRIDGES
Location:
Resident Engineer: Gregory Wood
Construction Contract Value: $6,302,900.00
Construction Bid Price: $1,226,800.00
Initial Construction Estimate: $1,056,565.00
District: District 5

Contracts (1) Progress
# 42231 -- Construction Contract
Emergency and Non Routine Structural Repairs to Bridges Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/19/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Initiated 06/04/2005
    Project Status Advertised 04/30/2005
    Project Management
    Final Design PS&E Received 04/27/2005
    Final Design PS&E to FAPRO 04/27/2005