Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- WINTHROP- BRIDGE REPLACEMENT, B-16-004=W42-001, ROUTE 145 (SARATOGA STREET) OVER BELLE ISLE INLET
The Belle Isle Bridge is one of only two access roadways to the Town of Winthrop. The bridge is Winthrop's only link to the City of Boston and carries the majority of commuter traffic. The bridge is a crucial link for emergency response vehicles. Although bridge inspections in 2002 and 2004 determined the bridge to be in fair condition, there are concerns that the condition of the bridge deck, slab, abutments, piles and bracing are approaching structural deficiency.
Location:
  • City of Boston
  • Town of Winthrop
  • Resident Engineer: Pasquale Mele
    Construction Contract Value: $4,289,840.00
    Construction Bid Price: $3,364,619.04
    Initial Construction Estimate: $3,997,363.00
    District: District 6

    Contracts (2) Progress
    # 57729 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 67665 -- Construction Contract
    Bridge Replacement (B-16-004=W-42-001) (Concrete) – Route 145 ((Saratoga Street) over Belle Isle Inlet. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/04/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/31/2005
    Project Status Initiated 03/01/2005
    Project Status Advertised 09/11/2010
    Project Management
    100% Design 100% Package Received 08/11/2009
    100% Design 100% Package Comments to DE 11/23/2009
    25% Design 25% Package Received 01/11/2008
    25% Design 25% Package Comments to DE 08/10/2007
    25% Design Design Public Hearing 06/16/2008
    75% Design 75% Package Received 02/13/2009
    Final Design PS&E Received 06/15/2010
    Final Design PS&E to FAPRO 09/08/2010