Project Description:
HINGHAM- RECONSTRUCTION & IMPROVEMENTS ON ROUTE 228, FROM QUEEN ANNE'S CORNER (ROUTE 53) TO MERRYMOUNT ROAD (PHASE II)
The scope of work includes pavement cold plane and overlay, full depth pavement construction, signal replacement, water and drainage improvements, signing and other incidental work. The length of project is 3.333 miles.
Location:
  • Town of Hingham
  • Resident Engineer: Peter Benkart
    Construction Contract Value: $4,764,794.00
    Construction Bid Price: $3,930,404.50
    Initial Construction Estimate: $4,351,100.00
    District: District 5

    Contracts (1) Progress
    # 54372 -- Construction Contract
    Hingham - Resurfacing and Related work on a section of Route 228 (Main Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/14/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 03/04/2005
    Project Status Advertised 08/11/2007
    Project Management
    100% Design 100% Package Received 04/25/2007
    100% Design 100% Package Comments to DE 06/12/2007
    25% Design 25% Package Received 03/20/2006
    25% Design 25% Package Comments to DE 07/24/2006
    25% Design Design Public Hearing 09/06/2006
    75% Design 75% Package Received 12/19/2006
    75% Design 75% Package Comments to DE 03/12/2007
    Final Design PS&E Received 07/31/2007
    Final Design PS&E to FAPRO 08/02/2007