DISTRICT 4- HERBICIDE APPLICATION AT VARIOUS LOCATIONS
This project consists of the application of an herbicide to various state right of ways to control nuisance vegetation.
Location:
Resident Engineer: Richard Pieslak
Construction Contract Value: $119,197.55
Construction Bid Price: $61,197.55
Initial Construction Estimate: $57,600.00
District: District 4
Current Status: Pending work review this contract is complete (as of 09/19/2006)
Additional Info: This contract is substansially complete. (as of 09/19/2006)

Contracts (1) Progress
# 41667 -- Construction Contract
District 4 Herbicide Application on Various Routes Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/27/2005
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Pending work review this contract is complete
    Additional Info
    This contract is substansially complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Initiated 03/15/2005
    Project Status Advertised 03/26/2005
    Project Management
    Final Design PS&E Received 03/21/2005
    Final Design PS&E to FAPRO 03/21/2005