Project Description:
HARVARD- LITTLETON- RESURFACING & RELATED WORK ON ROUTE 2
The Project limits are Route 2 in Harvard from the vicinity of the Littleton Road Bridge over Route 2 easterly about 1 mile to the Littleton Town Line, then continuing another 3.4 miles to the Boxborough Town Line, a total distance of approximately 4.4 miles. The project consists of cold planing and resurfacing, and related works, additional work includes minor box widenings to extend existing sub-standard acceleration and deceleration lanes.
Location:
  • Town of Harvard
  • Town of Littleton
  • Resident Engineer: William Walker
    Construction Contract Value: $4,837,378.00
    Construction Bid Price: $4,188,162.06
    Initial Construction Estimate: $4,609,204.00
    District: District 3

    Contracts (1) Progress
    # 58221 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 2 (ARRA) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/30/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/31/2005
    Project Status Initiated 03/22/2005
    Project Status Advertised 03/14/2009
    Project Management
    100% Design 100% Package Received 01/27/2009
    Final Design PS&E Received 02/27/2009
    Final Design PS&E to FAPRO 03/11/2009
    Consultant Contract Process NTP Issued 12/01/2008