| Project Description:
|
DISTRICT 4- CRACK SEALING AT VARIOUS LOCATIONS
|
| Location:
|
|
| Resident Engineer:
|
David Durkee |
| Construction Contract Value:
|
$462,770.00 |
| Construction Bid Price:
|
$425,770.00 |
| Initial Construction Estimate:
|
$300,000.00 |
| District:
|
District 4 |
| Current Status:
|
Completed work through estimate #6 - Two days of crack sealing on Granite Ave in Milton from Boston Line to Squantum St. (as of 12/16/2008) |
| Additional Info:
|
This contract has been completed and final estimate to follow soon. (as of 12/16/2008) |