| Project Description: |
LANCASTER- BRIDGE BETTERMENT, BR# L-02-016, SHIRLEY ROAD OVER ROUTE 2
|
| Location: |
|
| Resident Engineer: | Lisa Spezzaferro-Pelleti![]() |
| Construction Contract Value: | $676,942.50 |
| Construction Bid Price: | $588,942.50 |
| Initial Construction Estimate: | $520,625.75 |
| District: | District 3 |
| Current Status: | Painting of intermediate coat complete on bridge and railings. (as of 11/10/2006) |
|