| Project Description: |
BROCKTON- BRIDGE REPLACEMENT, B-25-032, WHITE AVENUE OVER SALISBURY BROOK
The proposed project consists of replacing the existing concrete superstructure with pre-stressed concrete deck beams and a composite concrete deck constructed on new concrete abutments on the back side of the existing stone abutments and reconstructing approximately 100 feet of White Avenue on each side of the bridge with new drainage, asphalt pavement, granite curbing and concrete sidewalks.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Municipality |
| Project Manager: | Stephen Soma![]() |
| Estimated Total Contract Cost: | $1,149,534.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 5 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||