Project Description:
BROCKTON- BRIDGE REPLACEMENT, B-25-032, WHITE AVENUE OVER SALISBURY BROOK
The proposed project consists of replacing the existing concrete superstructure with pre-stressed concrete deck beams and a composite concrete deck constructed on new concrete abutments on the back side of the existing stone abutments and reconstructing approximately 100 feet of White Avenue on each side of the bridge with new drainage, asphalt pavement, granite curbing and concrete sidewalks.
Location:
  • City of Brockton
  • Resident Engineer: Kenneth Belgrave
    Construction Contract Value: $1,149,534.00
    Construction Bid Price: $994,726.00
    Initial Construction Estimate: $1,332,971.50
    District: District 5

    Contracts (2) Progress
    # 37077 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/Replacement/Preservation Program. Final
    # 63793 -- Construction Contract
    Bridge Replacement Br. No. B-25-032 (Concrete) White Avenue over Salisbury Brook. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/20/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 04/08/2005
    Project Status Advertised 03/27/2010
    Project Management
    100% Design 100% Package Received 04/16/2009
    100% Design 100% Package Comments to DE 04/14/2009
    100% Design 100% Package Comments to DE 05/27/2009
    100% Design 100% Plans Complete 04/09/2009
    25% Design 25% Package Received 01/12/2007
    25% Design 25% Package Comments to DE 01/07/2008
    25% Design Design Public Hearing 03/26/2008
    75% Design 75% Package Received 11/12/2008
    75% Design 75% Package Comments to DE 01/28/2009
    Final Design PS&E Received 01/20/2010
    Final Design PS&E Received 02/17/2010
    Final Design PS&E to FAPRO 03/18/2010
    Consultant Contract Process Scope to DE 03/01/2006
    Consultant Contract Process NTP Issued 07/11/2008