Project Description:
BOSTON- CAMBRIDGE- BRIDGE REHABILITATION, B-16-009=C-01-002, CAMBRIDGE STREET OVER THE CHARLES RIVER (MEMORIAL & STORROW DRIVE) (AKA - LONGFELLOW BRIDGE) *EARLY ACTION - PHASE 1*
The Longfellow Bridge is a major transportation link between the City of Cambridge and the City of Boston and serves 28,600 vehicles daily, as well as bicycle and pedestrian traffic. An additional estimated 90,000 commuters use the MBTA’s Red Line Transit Service to cross this bridge on a reservation in the center of this structure. Ownership of the bridge has been transferred from the Department of Conservation and Recreation (DCR) to MassDOT's Highway Division which is overseeing the construction of early action repair work ahead of major rehabilitation work still under design.
Location:
  • City of Boston
  • City of Cambridge
  • Resident Engineer: Roderick Connelly III
    Construction Contract Value: $19,876,400.00
    Construction Bid Price: $17,773,373.50
    Initial Construction Estimate: $53,517,132.84
    District: District 6

    Contracts (3) Progress
    # 60493 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering for various projects
    # 62937 -- Non-system contract type
    Statewide-Owner's Representative-Will perform peer reviews and manage cost recovery and value engineering for various projects.
    # 63232 -- Construction Contract
    Longfellow Bridge Rehabilitation Including Painting (B-16-009=C-01-002) Cambridge Street over the Charles River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/12/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/16/2009
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 04/08/2005
    Project Status Advertised 01/30/2010
    Project Management
    75% Design 75% Package Received 09/22/2009
    75% Design 75% Package Comments to DE 11/13/2009
    Final Design PS&E Received 12/08/2009