Project Description:
HAMPDEN- BRIDGE SUPERSTRUCTURE REPLACEMENT, H-04-003, CHAPIN ROAD OVER SCANTIC RIVER
The existing bridge superstructure will be demolished and replaced. The superstructure shall consist of one 59.5-foot span with composite steel stringers and a concrete deck. The existing abutments and wingwalls will be modified and re-used.
Location:
  • Town of Hampden
  • Resident Engineer: James White
    Construction Contract Value: $1,255,824.50
    Construction Bid Price: $1,194,847.50
    Initial Construction Estimate: $1,379,522.00
    District: District 2
    Current Status: Bridge under construction (as of 04/15/2008)

    Contracts (1) Progress
    # 53472 -- Construction Contract
    Hampden - Bridge Superstructure Replacement (H-04-003) Chapin Road over the Scantic River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/14/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge under construction
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 04/12/2005
    Project Status Advertised 10/21/2006
    Project Management
    100% Design 100% Package Received 07/24/2006
    100% Design 100% Package Comments to DE 08/09/2006
    25% Design 25% Package Received 10/12/2005
    25% Design 25% Package Comments to DE 11/18/2005
    25% Design Design Public Hearing 06/15/2006
    75% Design 75% Package Received 01/27/2006
    75% Design 75% Package Comments to DE 03/27/2006
    Final Design PS&E Received 08/29/2006
    Final Design PS&E to FAPRO 09/01/2006
    Consultant Contract Process Scope to DE 08/22/2003
    Consultant Contract Process NTP Issued 09/09/2003
    Consultant Contract Process Workhours Approved 09/04/2003