Project Description:
PELHAM- BRIDGE REPLACEMENTS, P-04-006, MEETINGHOUSE ROAD OVER AMETHYST BROOK & P-04-007, MEETINGHOUSE ROAD OVER HARRIS BROOK
The purpose of this project is to replace the two bridges on Meetinghouse Road that cross over Amethyst and Harris Brooks. Both bridges are single span, one lane steel beam structures. They will be replaced with single span rigid frame structures with cast in place footings and wingwalls. The span length will be 22 - 24 ft with a width of 16 ft (13 ft curb to curb).
Location:
  • Town of Pelham
  • Resident Engineer: Anthony Kuralowicz
    Construction Contract Value: $2,109,505.50
    Construction Bid Price: $1,878,005.00
    Initial Construction Estimate: $1,842,000.00
    District: District 2

    Contracts (5) Progress
    # 57463 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 73478 -- Design -- Bridge Open End
    Work will consist of inspection of MassDOT owned Dams and Spillway structures and the design of repairs and/or rehabilitation of the dams and spillway structures. Final
    # 77877 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 85011 -- Construction Contract
    Bridge Replacements (Steel) Br. Nos. P-04-006 & P-04-007 Meetinghouse Road over the Amethyst and Harris Brooks Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/24/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/26/2005
    Project Status Initiated 04/14/2005
    Project Status Advertised 09/20/2014
    Project Management
    25% Design 25% Package Received 10/21/2013
    25% Design 25% Package Comments to DE 11/27/2013
    25% Design 25% Package Approved 02/20/2014
    25% Design Design Public Hearing 01/29/2014
    75% Design 75% Package Received 05/09/2014
    75% Design 75% Package Comments to DE 06/23/2014
    Final Design PS&E Received 08/12/2014
    Final Design PS&E to FAPRO 09/08/2014
    Consultant Contract Process Scope to DE 05/01/2005
    Consultant Contract Process NTP Issued 08/08/2005