Project Description:
BROCKTON- RECONSTRUCTION OF ROUTE 27, PLEASANT STREET AT WEST STREET AND WESTGATE MALL DRIVE
The proposed project consists of roadway modifications and the reconstruction of Route 27, Pleasant Street, West Street and Westgate Mall Road. Vehicular operations are anticipated to be improved as a result of the proposed roadway widening, geometric improvements, new traffic signals and interconnection of signalized intersections.
Location:
  • City of Brockton
  • Resident Engineer: Ronald Strangfeld
    Construction Contract Value: $3,549,136.00
    Construction Bid Price: $2,998,788.15
    Initial Construction Estimate: $4,924,498.16
    District: District 5

    Contracts (1) Progress
    # 59129 -- Construction Contract
    Roaway Reconstruction and Related Work on Route 27 (Reynolds Memorial Highway) at Pleasant and West Streets and Westgate Mall Drive. (ARRA PRoject) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/30/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/20/2005
    Project Status Initiated 04/20/2005
    Project Status Advertised 06/20/2009
    Project Management
    100% Design 100% Package Received 12/09/2008
    100% Design 100% Package Comments to DE 03/13/2009
    25% Design 25% Package Received 02/02/2006
    25% Design 25% Package Comments to DE 04/20/2006
    25% Design Design Public Hearing 02/28/2007
    75% Design 75% Package Received 09/24/2007
    75% Design 75% Package Received 05/27/2008
    75% Design 75% Package Comments to DE 08/21/2008
    Final Design PS&E Received 05/11/2009
    Final Design PS&E to FAPRO 06/10/2009