Project Description: |
BROCKTON- RECONSTRUCTION OF ROUTE 27, PLEASANT STREET AT WEST STREET AND WESTGATE MALL DRIVE
The proposed project consists of roadway modifications and the reconstruction of Route 27, Pleasant Street, West Street and Westgate Mall Road. Vehicular operations are anticipated to be improved as a result of the proposed roadway widening, geometric improvements, new traffic signals and interconnection of signalized intersections.
|
Location: |
|
Resident Engineer: | Ronald Strangfeld |
Construction Contract Value: | $3,549,136.00 |
Construction Bid Price: | $2,998,788.15 |
Initial Construction Estimate: | $4,924,498.16 |
District: | District 5 |
|
Bridges |
|
|
|
|