Project Description:
BELCHERTOWN- PAVEMENT REHABILITATION & RELATED WORK ON ROUTE 181, FROM MAPLE ST TO BELCHERTOWN/PALMER TOWN LINE (5.5 MILES)
The limits of this pavement rehabilitation project are along town-owned Route 181 from the Maple Street intersection southerly to the Belchertown/Palmer town line, for a total length of approximately 5.65 miles. Route 181 will be reconstructed to a final lane configuration of two 11 foot lanes and two 4 foot shoulders. Safety improvements to be constructed as part of this project include minor sight distance improvements, bicycle accommodation improvements, sidewalk reconstruction, roadway drainage improvements, guardrail and the installation of pavement markings and signage.
Location:
  • Town of Belchertown
  • Resident Engineer: Colleen Ford
    Construction Contract Value: $8,930,640.25
    Construction Bid Price: $8,888,621.37
    Initial Construction Estimate: $8,709,816.50
    District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 84978 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Route 181 (Mill Valley Road and Franklin Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/24/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: Other types not listed
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Tabled 04/21/2005
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 01/04/2006
    Project Status Initiated 04/25/2005
    Project Status Advertised 09/13/2014
    Project Management
    100% Design 100% Package Received 10/17/2011
    100% Design 100% Package Comments to DE 08/24/2012
    100% Design 100% Plans Approved 08/24/2012
    25% Design 25% Package Received 06/06/2007
    25% Design 25% Package Comments to DE 10/02/2007
    25% Design 25% Package Approved 04/18/2008
    25% Design Design Public Hearing 11/19/2008
    75% Design 75% Package Received 06/08/2009
    75% Design 75% Package Comments to DE 03/10/2010
    Final Design PS&E Received 10/01/2013
    Final Design PS&E Received 12/16/2013
    Final Design PS&E Received 01/22/2014
    Final Design PS&E Received 02/18/2014
    Final Design PS&E Received 08/26/2014
    Final Design PS&E to FAPRO 02/21/2014
    Final Design PS&E to FAPRO 09/10/2014