Project Description:
CHICOPEE- RECONSTRUCTION & RELATED WORK ON FULLER ROAD, FROM MEMORIAL DR (RTE 33) TO SHAWINIGAN DR (2.0 MILES)
The project includes pavement rehabilitation, drainage improvements and upgrading the existing traffic signals for a closed loop coordination on this city-owned street. Other work includes bicycle and pedestrian accommodation improvement. The project extends from Memorial Drive (Route 33) easterly to Shawinigan Drive for a total length of 2 miles.
Location:
  • City of Chicopee
  • Construction Begins: Autumn 2020
    Resident Engineer: Jessica Gaudet
    Construction Bid Price: $9,394,879.50
    District: District 2

    Contracts (1) Progress
    # 112711 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Fuller Road Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/24/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 04/25/2005
    Project Status Advertised 08/29/2020
    Project Management
    100% Design 100% Package Received 03/05/2020
    100% Design 100% Package Comments to DE 04/10/2020
    25% Design 25% Package Received 03/31/2017
    25% Design 25% Package Comments to DE 07/27/2017
    25% Design Design Public Hearing 02/27/2018
    75% Design 75% Package Received 08/22/2018
    75% Design 75% Package Comments to DE 11/08/2018
    Final Design PS&E Received 07/13/2020
    Final Design PS&E Received - Resub 1 08/13/2020