Project Description:
WINCHENDON- MULTI-USE TRAIL CONSTRUCTION (NORTH CENTRAL PATHWAY - PHASE V) INCLUDES W-39-023, W-39-024 & W-39-028
This project consists of the construction of a shared use path in Winchendon from the vicinity of its intersection with North Ashburnham Road to the vicinity of Glenallen Street, a distance of approximately 2.1 miles. The proposed path construction is along lower rail bed and upper rail bed segments of former railroad lines. Along the lower rail bed, it includes refurbishing three bridges over the Millers River with new wood decks and handrails. The project includes installation of park benches, drainage system improvements, guardrail, roadside grading, pavement markings and signs, and other incidental work. This is the fifth in a series of planned segments, which, when combined, will provide for a continuous North Central Pathway from Gardner to the New Hampshire border, a distance of approximately 16 miles.
Location:
  • Town of Winchendon
  • Resident Engineer: Matthew Minihan
    Construction Contract Value: $1,987,709.81
    Construction Bid Price: $1,693,423.00
    Initial Construction Estimate: $1,589,636.58
    District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 83127 -- Construction Contract
    North Central Multi-use Pathway Construction and Related Work (Including 3 Bridges). (Phase V) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/12/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 04/25/2005
    Project Status Advertised 06/28/2014
    Project Management
    100% Design 100% Package Received 02/14/2013
    100% Design 100% Package Comments to DE 09/13/2013
    25% Design 25% Package Received 12/01/2006
    25% Design 25% Package Comments to DE 04/25/2007
    25% Design Design Public Hearing 04/29/2008
    75% Design 75% Package Received 12/28/2011
    75% Design 75% Package Comments to DE 07/16/2012
    Final Design PS&E Received 06/18/2014
    Final Design PS&E Received 03/24/2015
    Final Design PS&E to FAPRO 06/25/2014