Project Description:
EASTHAMPTON- SOUTHAMPTON- TRAIL CONSTRUCTION (MANHAN RAIL TRAIL), FROM SOUTH STREET TO COLEMAN ROAD
The proposed trail will be about ¾-mile and constructed along an abandoned railroad between Coleman Road in Southampton and South Street in Easthampton, where it meets the completed portion of the Manhan Trail in Easthampton.
Location:
  • Town of Easthampton
  • Resident Engineer: Joseph Burek
    Construction Contract Value: $247,009.00
    Construction Bid Price: $735,210.00
    Initial Construction Estimate: $1,181,009.54
    District: District 2

    Contracts (1) Progress
    # 67598 -- Construction Contract
    Construction of a Section of the Manhan Rail Trail. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/31/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 04/26/2005
    Project Status Advertised 09/11/2010
    Project Management
    100% Design 100% Package Received 04/21/2010
    100% Design 100% Package Comments to DE 07/20/2010
    100% Design 100% Plans Approved 08/12/2010
    100% Design 100% Plans Complete 07/20/2010
    25% Design Design Public Hearing 03/24/2010
    75% Design 75% Package Received 10/19/2009
    75% Design 75% Package Comments to DE 11/09/2009
    75% Design 75% Plans Approved 01/22/2010
    Final Design PS&E Received 08/30/2010
    Final Design PS&E to FAPRO 09/08/2010
    Final Design PS&E to FAPRO 09/24/2010