WESTFIELD- RECONSTRUCTION OF ROUTE 187 (FEEDING HILLS ROAD), FROM 400 METERS EAST OF OLD FEEDING HILLS ROAD TO AGAWAM T.L. (.73 MILES) INCLUDES REHAB OF W-25-054 & W-25055 CULVERTS
This project is part of the three-phase Route 187 project. The project involves roadway reconstruction, drainage and other improvements from near the Sherman Mill Bridge to the Agawam city line. The total project length is 0.73 miles.
Location:
  • City of Westfield
  • Resident Engineer: Joseph McCarthy
    Construction Contract Value: $4,238,301.00
    Construction Bid Price: $3,891,977.30
    Initial Construction Estimate: $3,916,120.00
    District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 79599 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Replacement of 2 Culverts) on a Section of Route187 (Feeding Hills Road). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 04/26/2005
    Project Status Advertised 09/07/2013
    Project Management
    100% Design 100% Package Received 03/28/2011
    100% Design 100% Package Received 02/25/2013
    100% Design 100% Package Comments to DE 11/20/2011
    100% Design 100% Package Comments to DE 04/19/2013
    25% Design 25% Package Comments to DE 05/03/2000
    25% Design Design Public Hearing 02/27/2013
    75% Design 75% Package Received 06/13/2008
    75% Design 75% Package Comments to DE 09/22/2008
    Final Design PS&E Received 07/17/2013
    Final Design PS&E Received 08/27/2013
    Final Design PS&E to FAPRO 09/04/2013