| Project Description: |
WESTFIELD- RECONSTRUCTION OF ROUTE 187 (FEEDING HILLS ROAD), FROM 400 METERS EAST OF OLD FEEDING HILLS ROAD TO AGAWAM T.L. (.73 MILES) INCLUDES REHAB OF W-25-054 & W-25055 CULVERTS
This project is part of the three-phase Route 187 project. The project involves roadway reconstruction, drainage and other improvements from near the Sherman Mill Bridge to the Agawam city line. The total project length is 0.73 miles.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Municipality |
| Project Manager: | Shawn Holland![]() |
| Estimated Total Contract Cost: | $4,238,301.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 2 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||