SOUTHWICK- RAIL TRAIL EXTENSION, FROM POINT GROVE ROAD TO WESTFIELD CITY LINE (PHASE II)
This project consists of the construction of Phase II of a multiple use 3.5 mile trail along a segment of the former Penn Central Railroad from the Westfield Town Line to the intersection of the right-of-way with Phase I north of Point Grove Road. The construction of the trail will serve to improve the abandoned railbed currently overgrown with weeds and abused by trespassers while preserving approximately 48 acres of land as “open space” for restricted recreational use. Additional work outside of this right-of-way will include the design and preparation of easements for access to the trail from local streets, neighborhoods, schools and the central business district. The proposed trail construction includes utility relocation, traffic signs and pavement markings, fencing and barriers, drainage, erosion control and bank stabilization, parking and picnic areas, scenic overlooks, landscaping and rest areas. When complete, the Southwick Rail Trail, a total of 7.1 miles, will connect with the Farmington Valley Greenway for a total of 32 miles of continuous trail.
Location:
  • Town of Southwick
  • Resident Engineer: Hannah Lapointe
    Construction Contract Value: $1,649,462.00
    Construction Bid Price: $1,482,420.00
    Initial Construction Estimate: $1,876,638.10
    District: District 2

    Contracts (1) Progress
    # 60077 -- Construction Contract
    Rail Trail Construction from Point Grove Road to Westfield City Line (PhaseII). (Re_Advertised) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/08/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 04/26/2005
    Project Status Advertised 08/25/2007
    Project Status Advertised 08/08/2009
    Project Management
    100% Design 100% Package Received 09/05/2006
    100% Design 100% Package Received 10/01/2008
    100% Design 100% Package Comments to DE 01/25/2007
    100% Design 100% Package Comments to DE 06/12/2009
    100% Design 100% Package Comments to DE 07/17/2009
    25% Design 25% Package Received 07/25/2005
    25% Design 25% Package Comments to DE 10/19/2005
    25% Design Design Public Hearing 12/14/2005
    25% Design 25% Plans Complete 08/26/2005
    75% Design 75% Package Received 05/09/2006
    75% Design 75% Package Comments to DE 07/10/2006
    Final Design PS&E Received 08/23/2007
    Final Design PS&E Received 11/02/2007
    Final Design PS&E Received 10/01/2008
    Final Design PS&E Received 06/12/2009
    Final Design PS&E Received 07/27/2009
    Final Design PS&E to FAPRO 08/17/2007