| Project Description: |
SOUTHWICK- (PHASE I) RECONSTRUCTION WITH CULVERT REPLACEMENT, ROUTE 168 (CONGAMOND ROAD)
The project consists of replacing an existing culvert. A temporary traffic signal will maintain alternative single lane of traffic during construction.
|
| Location: |
|
| Resident Engineer: | Joseph Borowiec![]() |
| Construction Contract Value: | $1,663,284.00 |
| Construction Bid Price: | $1,477,531.50 |
| Initial Construction Estimate: | $942,560.00 |
| District: | District 2 |
| Current Status: | Road under construction (as of 10/02/2006) |
| Additional Info: | Work suspended for winter shutdown. When work resumes in Spring 2008, daily lane closures/restrictions for the remainder of the project. (as of 12/13/2007) |
|