Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SPRINGFIELD- RECONSTRUCTION OF STATE STREET (CORRIDOR IMPROVEMENTS)
The work under this project consists of the reconstruction of approximately 3.2 miles of the State Street Corridor. The work includes roadway improvements, pavement reconstruction, installation of granite curb, sidewalks, upgrade and coordination of the existing signal systems.
Location:
  • City of Springfield
  • Resident Engineer: Mark Shea
    Construction Contract Value: $18,092,857.00
    Construction Bid Price: $15,932,074.50
    Initial Construction Estimate: $11,396,886.50
    District: District 2

    Contracts (1) Progress
    # 54589 -- Construction Contract
    Springfield - Roadway Reconstruction and Related Work on State Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/30/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 11/16/2005
    Project Status Initiated 04/26/2005
    Project Status Advertised 09/22/2007
    Project Management
    100% Design 100% Package Received 02/22/2007
    100% Design 100% Package Comments to DE 05/01/2007
    100% Design 100% Plans Complete 08/31/2007
    25% Design 25% Package Received 01/04/2006
    25% Design 25% Package Comments to DE 04/19/2006
    25% Design 25% Package Approved 05/17/2006
    25% Design Design Public Hearing 05/10/2006
    75% Design 75% Package Received 09/11/2006
    75% Design 75% Package Comments to DE 11/15/2006
    Final Design PS&E Received 08/31/2007
    Final Design PS&E to FAPRO 08/31/2007