Project Description:
SPRINGFIELD- NORTH END & BRIGHTWOOD INFRASTRUCTURE IMPROVEMENTS, FROM AMTRAK OVERPASS TO OSGOOD STREET (SOUTHERLY SEGMENT)
Work includes road rehabilitation, sidewalk reconstruction, streetscape and pedestrian connections. The project includes Main Street from the AMTRAK overpass north to Osgood Street (0.73 miles) and Riverside Road at M Street (possible bikepath connection).
Location:
  • City of Springfield
  • Resident Engineer: Anthony Kuralowicz
    Construction Contract Value: $2,729,953.00
    Construction Bid Price: $2,226,616.50
    Initial Construction Estimate: $2,496,392.00
    District: District 2

    Contracts (3) Progress
    # 41928 -- Design -- Highway
    Rehabilitate and improve the road and pedestrian infrastructure in the Brightwood/North End area of Springfield. Final
    # 64325 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68177 -- Construction Contract
    SPRINGFIELD - Roadway Reconstruction and Related Work on Sections of Main Street from Osgood Street to AMTRAK Overpass (Southerly Segment) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/02/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/09/2005
    Project Status Initiated 04/26/2005
    Project Status Advertised 02/19/2011
    Project Management
    100% Design 100% Package Received 12/22/2010
    100% Design 100% Package Comments to DE 01/28/2011
    100% Design 100% Plans Approved 01/18/2011
    25% Design 25% Package Received 11/15/2007
    25% Design 25% Package Comments to DE 01/08/2008
    25% Design Design Public Hearing 08/07/2008
    75% Design 75% Package Received 02/02/2009
    75% Design 75% Package Comments to DE 03/03/2009
    Final Design PS&E Received 02/09/2011
    Final Design PS&E to FAPRO 02/16/2011
    Consultant Contract Process Scope to DE 06/16/2005
    Consultant Contract Process NTP Issued 02/16/2006
    Consultant Contract Process Workhours Approved 10/03/2005