Project Description: |
EASTHAMPTON- BRIDGE REPLACEMENT, E-05-019, HENDRICK STREET OVER BROAD BROOK
The purpose of this project is to replace the superstructure of the Hendrick Street over Broad Brook bridge with precast butted concrete deck beams and a concrete slab deck. The construction will be done in three stages with one lane of traffic open utilizing a temporary traffic signal.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Project Manager: | Gautam Sen![]() |
Estimated Total Contract Cost: | $1,372,746.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
Total Estimated Project Cost: | $1,820,190.00 |
District: | District 2 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|