Project Description: |
EASTHAMPTON- BRIDGE REPLACEMENT, E-05-019, HENDRICK STREET OVER BROAD BROOK
The purpose of this project is to replace the superstructure of the Hendrick Street over Broad Brook bridge with precast butted concrete deck beams and a concrete slab deck. The construction will be done in three stages with one lane of traffic open utilizing a temporary traffic signal.
|
Location: |
|
Resident Engineer: | Edward Evans |
Construction Contract Value: | $1,372,746.00 |
Construction Bid Price: | $1,158,692.47 |
Initial Construction Estimate: | $1,420,736.00 |
Total Estimated Project Cost: | $1,820,190.00 |
District: | District 2 |
|