Project Description:
DISTRICT 4- SCHEDULED & EMERGENCY STRUCTURAL REPAIRS (NORFOLK & SUFFOLK COUNTIES - CONTRACT #3)
Location:
Resident Engineer: Lonardi Philogene
Construction Contract Value: $4,251,900.00
Construction Bid Price: $1,791,900.00
Initial Construction Estimate: $1,475,500.00
District: District 4
Current Status: Structural repairs were performed at the following locations during the month of Nov. 2008. Lowell- Rte 495 @ Guilford RR Tyngsborough- Acrow Bridge @ Merrimac River. East Boston- Rte 1A @ Saratoga St. Medford- - Rte 16 @ Rte 93 S.B. Concord- Old Stow Rd. @ MBCR Quincy - Furnace Brook Parkway @ Rte 93. Wakefield- Rte 128 @ Rte 129 (as of 01/05/2009)

Contracts (2) Progress
# 52738 -- Construction Contract
Scheduled and Emergency Bridge Structural Repairs. (# Seperate Contracts) Completed
# 52740 -- Construction Contract
Scheduled and Emergency Bridge Structural Repairs (3 Seperate Contracts) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/14/2007
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Structural repairs were performed at the following locations during the month of Nov. 2008. Lowell- Rte 495 @ Guilford RR Tyngsborough- Acrow Bridge @ Merrimac River. East Boston- Rte 1A @ Saratoga St. Medford- - Rte 16 @ Rte 93 S.B. Concord- Old Stow Rd. @ MBCR Quincy - Furnace Brook Parkway @ Rte 93. Wakefield- Rte 128 @ Rte 129
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/27/2005
    Project Status Initiated 05/23/2005
    Project Status Advertised 04/21/2007
    Project Management
    Final Design PS&E Received 11/18/2006
    Final Design PS&E to FAPRO 12/22/2006