WORCESTER- NORTH MAIN STREET GATEWAY IMPROVEMENTS
The purpose of this project is to replace the signal at Grove Street and Salisbury, install a new signal at the intersection of Grove and Faraday Streets, and interconnect a number of intersections on the Salisbury, Grove and Highland Streets corridors. The work also includes resurfacing sections of Salisbury and Grove Streets.
Location:
  • City of Worcester
  • Resident Engineer: Steven Miller
    Construction Contract Value: $1,728,693.00
    Construction Bid Price: $1,494,994.15
    Initial Construction Estimate: $1,690,939.50
    District: District 3

    Contracts (1) Progress
    # 68027 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) on a Section of North Main Street at Highland, Grove and Salisbury Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/07/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 05/27/2005
    Project Status Initiated 05/23/2005
    Project Status Advertised 09/11/2010
    Project Management
    100% Design 100% Package Received 03/23/2010
    100% Design 100% Package Comments to DE 05/06/2010
    25% Design 25% Package Received 04/07/2008
    25% Design 25% Package Received 07/24/2008
    25% Design 25% Package Comments to DE 10/07/2008
    25% Design 25% Package Comments to DE 04/28/2009
    25% Design Design Public Hearing 01/21/2009
    75% Design 75% Package Received 10/19/2009
    75% Design 75% Package Comments to DE 01/05/2010
    Final Design PS&E Received 08/06/2010
    Final Design PS&E to FAPRO 09/08/2010