WORCESTER- NORTH MAIN STREET GATEWAY IMPROVEMENTS
The purpose of this project is to replace the signal at Grove Street and Salisbury, install a new signal at the intersection of Grove and Faraday Streets, and interconnect a number of intersections on the Salisbury, Grove and Highland Streets corridors. The work also includes resurfacing sections of Salisbury and Grove Streets.
Location:
  • City of Worcester
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $1,728,693.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information