Project Description:
DANVERS- LYNNFIELD- PEABODY- TRAFFIC SIGN REPLACEMENT AND SAFETY IMPROVEMENTS, I-95
This project will replace and update all overhead and ground-mounted guide sign panels, exit gore, warning, regulatory, and route marker panels on the I-95 mainline from the U.S. 1 NB/S.R. 129 EB interchange (Exit 44B) in Lynnfield northerly to the U.S. 1 SB interchange (Exit 46) in Danvers and on the S.R. 128 mainline from Lowell Street (Exit 26) in Peabody southerly to the I-95 interchange (Exit 28) in Peabody.
Location:
  • Town of Danvers
  • Town of Lynnfield
  • City of Peabody
  • Resident Engineer: Amanda Klemm
    Construction Contract Value: $1,439,211.00
    Construction Bid Price: $1,279,205.00
    Initial Construction Estimate: $1,481,475.00
    District: District 4

    Contracts (1) Progress
    # 51811 -- Construction Contract
    Danvers-Lynnfield-Peabody Overhead Guide Sign Replacement and Related Work on I-95 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/24/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Initiated 06/01/2005
    Project Status Advertised 11/19/2005
    Project Management
    100% Design 100% Package Received 09/13/2005
    100% Design 100% Package Comments to DE 09/16/2005
    100% Design 100% Plans Approved 09/16/2005
    25% Design 25% Package Received 07/13/2005
    75% Design 75% Package Received 07/28/2005
    75% Design 75% Package Comments to DE 08/19/2005
    75% Design 75% Plans Approved 08/17/2005
    Final Design PS&E Received 09/15/2005
    Final Design PS&E to FAPRO 09/19/2005
    Consultant Contract Process NTP Issued 06/08/2005