Project Description:
SPENCER- RECONSTRUCTION OF MAPLE STREET (ROUTE 31) FROM BEMIS STREET TO MAIN STREET (ROUTE 9)
The work under this project consists of the reconstruction of Maple Street (Route 31 Phase 1) beginning just south of the intersection of Bemis Street and continuing northerly for a distance of approximately 2,900 linear feet to the intersection with Main Street (Route 9/31). The project shall include roadway rehabilitation, sidewalk improvements with ADA conforming wheelchair ramps, drainage improvements, improvements to traffic operations, new signs and pavement markings, pedestrian and streetscape enhancements.
Location:
  • Town of Spencer
  • Resident Engineer: Paul Thompson
    Construction Contract Value: $2,232,087.00
    Construction Bid Price: $2,400,000.00
    Initial Construction Estimate: $2,615,013.50
    District: District 3

    Contracts (2) Progress
    # 57850 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Maple Street (Route 31). Completed
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/16/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Tabled 04/21/2005
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/31/2006
    Project Status Initiated 06/01/2005
    Project Status Advertised 09/06/2008
    Project Status Advertised 01/24/2009
    Project Management
    100% Design 100% Package Received 06/18/2008
    100% Design 100% Package Comments to DE 08/01/2008
    25% Design 25% Package Received 11/02/2006
    25% Design 25% Package Comments to DE 03/31/2007
    25% Design Design Public Hearing 02/06/2007
    75% Design 75% Package Received 10/16/2007
    75% Design 75% Package Comments to DE 02/20/2008
    Final Design PS&E Received 01/12/2009