Project Description:
DENNIS- YARMOUTH- CAPE COD RAIL TRAIL EXTENSION, INCLUDES REPLACING D-07-015, CCRT OVER ROUTE 134 & Y-01-009, CCRT OVER STATION AVENUE
Work on this project consists of the construction of a 3.7 mile multi-user path. The path is an extension of the Cape Cod Rail Trail. The proposed path begins 2,500 feet west of Station Avenue, at the Old Townhouse Road Park and extends to just east of Route 134 where it meets the existing Cape Cod Rail Trail.
Location:
  • Town of Dennis
  • Town of Yarmouth
  • Resident Engineer: Malcolm Lavalley
    Construction Contract Value: $7,563,942.76
    Construction Bid Price: $6,675,352.40
    Initial Construction Estimate: $6,636,000.00
    District: District 5

    Contracts (5) Progress
    # 54138 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 85002 -- Construction Contract
    Construction of the Cape Cod Rail Trail Extension (Phase I) Including 2 Bridges Br. Nos. Y-01-009 & D-07-015 (Pre-Fab Steel Trusses) over Station Avenue and Route 134 (East-We Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/25/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 10/26/2005
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 08/18/2014
    100% Design 100% Package Comments to DE 09/15/2014
    25% Design 25% Package Received 03/02/2011
    25% Design 25% Package Comments to DE 04/29/2014
    25% Design 25% Package Comments to DE 07/14/2014
    25% Design Design Public Hearing 05/20/2013
    75% Design 75% Package Received 03/31/2014
    75% Design 75% Package Comments to DE 07/25/2014
    Final Design PS&E Received 09/16/2014
    Final Design PS&E to FAPRO 09/17/2014