Project Description:
ROYALSTON- BRIDGE REPLACEMENT, R-12-001, STOCKWELL ROAD OVER LAWRENCE BROOK
The proposed structure shall be a twin precast concrete box culvert and cast-in-place wingwalls. The proposed bridge rail shall be Delaware Thrie Beam system. The footprint of the new structure shall approximately match the footprint of the existing structure. The bridge is currently proposed to be closed during construction.
Location:
  • Town of Royalston
  • Resident Engineer: Matthew Minihan
    Construction Contract Value: $681,695.00
    Construction Bid Price: $616,905.10
    Initial Construction Estimate: $523,810.00
    District: District 2

    Contracts (5) Progress
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64326 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 77872 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 79145 -- Construction Contract
    Bridge Replacement (R-12-001) (Carbon Fiber Tube) Stockwell Road over Lawrence Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/04/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 06/23/2005
    Project Status Advertised 08/10/2013
    Project Management
    100% Design 100% Package Received 02/26/2008
    100% Design 100% Package Received 03/06/2013
    100% Design 100% Package Comments to DE 06/18/2008
    100% Design 100% Package Comments to DE 03/26/2013
    25% Design 25% Package Received 06/23/2006
    25% Design 25% Package Received 01/03/2013
    25% Design 25% Package Comments to DE 09/27/2006
    25% Design 25% Package Comments to DE 02/04/2013
    25% Design Design Public Hearing 08/22/2007
    75% Design 75% Package Received 02/05/2007
    75% Design 75% Package Received 01/03/2013
    75% Design 75% Package Comments to DE 04/04/2007
    75% Design 75% Package Comments to DE 02/04/2013
    Final Design PS&E Received 06/12/2013
    Final Design PS&E to FAPRO 08/05/2013
    Consultant Contract Process Scope to DE 08/29/2005
    Consultant Contract Process NTP Issued 02/01/2006
    Consultant Contract Process Workhours Approved 01/24/2006