NORTHBRIDGE- BRIDGE REPLACEMENT, N-21-002, ROUTE 122 (PROVIDENCE ROAD) OVER THE BLACKSTONE RIVER (AKA ROSAIRE "ROSS" ROJETTE MEMORIAL BRIDGE)
The work involves the replacment of the bridge carrying State Route 122 (Providence Road) over the Blackstone River with a 32-foot wide (measured curb-to-curb) bridge. The new bridge will have a 6.5-foot sidewalk on the east side.
Location:
  • Town of Northbridge
  • Resident Engineer: Hassan Valipour
    Construction Contract Value: $3,954,850.00
    Construction Bid Price: $3,149,000.00
    Initial Construction Estimate: $4,068,198.00
    District: District 3

    Contracts (3) Progress
    # 54830 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 68140 -- Construction Contract
    NORTHBRIDGE - Bridge Replacement (N-21-002) (Steel) - Route 122 (Providence Road) over the Blackstone River (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/20/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 07/21/2005
    Project Status Advertised 09/25/2010
    Project Management
    100% Design 100% Package Comments to DE 08/18/2010
    25% Design 25% Package Received 10/17/2007
    25% Design 25% Package Comments to DE 08/20/2009
    25% Design Design Public Hearing 05/06/2009
    75% Design 75% Package Received 08/05/2009
    75% Design 75% Package Received 06/23/2010
    75% Design 75% Package Comments to DE 08/10/2010
    Final Design PS&E Received 09/17/2010
    Final Design PS&E to FAPRO 09/22/2010
    Consultant Contract Process Scope to DE 09/21/2005
    Consultant Contract Process NTP Issued 07/11/2008