Project Description:
OXFORD- CULVERT REPLACEMENT, O-06-001, COMINS ROAD OVER FRENCH RIVER
The purpose of this project is to replace the culvert carrying Comins Road over French River under the auspices of the“Footprint” Bridge Replacement Program. The existing structure built in 1979 is a two barrel corrugated galvanized steel culvert structure which is now structurally deficient. It is anticipated that the structure will be replaced with a pre-cast three sided bridge. The proposed bridge curb to curb width is 28 feet with no sidewalks. The curb to curb width of the roadway over the bridge will be 28 feet matching the existing roadway width. The length of the project is 386 feet. The roadway is functionally classified as an urban collector/rural minor collector. There will be minor roadway reconstruction and resurfacing work approaching the bridge. The bridge will be closed during construction and a detour will be provided.
Location:
  • Town of Oxford
  • Resident Engineer: Jean-Pierre Telemaque
    Construction Contract Value: $968,194.00
    Construction Bid Price: $817,013.00
    Initial Construction Estimate: $1,042,895.82
    District: District 3

    Contracts (4) Progress
    # 51304 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77972 -- Construction Contract
    Culvert Replacement (O-06-001) (Concrete) - Comins Road over the French River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/03/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 07/21/2005
    Project Status Advertised 06/22/2013
    Project Management
    25% Design 25% Package Received 07/03/2008
    25% Design 25% Package Received 05/11/2012
    25% Design 25% Package Comments to DE 07/27/2012
    25% Design Design Public Hearing 10/15/2012
    75% Design 75% Package Received 01/18/2013
    75% Design 75% Package Comments to DE 02/15/2013
    Final Design PS&E Received 05/13/2013
    Final Design PS&E Received 06/07/2013
    Final Design PS&E to FAPRO 06/18/2013
    Consultant Contract Process Scope to DE 09/25/2008