UXBRIDGE- BRIDGE REPLACEMENT, U-02-001, STATE ROUTE 122 (MAIN STREET) OVER THE BLACKSTONE RIVER
The project consists of replacing the existing bridge that carries Route 122 (Main Street) over the Blackstone River in Uxbridge, and the associated approach roadway. The existing concrete bridge which was built in 1931 is about 125 feet long, has a 41-foot curb-to-curb width and is in poor condition. The proposed replacement is a single-span steel beam structure supported on concrete abutments. To minimize impact, the new bridge will be established on the existing footprint and right-of-way, and so will be approximately 44 feet wide, with a 6.5 foot sidewalk located on the north side.
Location:
  • Town of Uxbridge
  • Resident Engineer: Scott Fitzgerald
    Construction Contract Value: $3,090,884.00
    Construction Bid Price: $2,657,725.85
    Initial Construction Estimate: $4,103,915.00
    District: District 3

    Contracts (2) Progress
    # 59591 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 66843 -- Construction Contract
    Bridge Replacement (U-02-001) (Steel) - Route 122 (Main Street) over the Blackstone River (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/10/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 07/26/2005
    Project Status Advertised 08/21/2010
    Project Management
    25% Design 25% Package Received 02/23/2009
    25% Design 25% Package Received 07/15/2009
    25% Design 25% Package Comments to DE 03/16/2009
    25% Design Design Public Hearing 09/16/2009
    75% Design 75% Package Received 02/19/2010
    75% Design 75% Package Comments to DE 04/27/2010
    Final Design PS&E Received 06/18/2010
    Final Design PS&E Received 08/17/2010
    Final Design PS&E to FAPRO 08/18/2010
    Consultant Contract Process Scope to DE 08/29/2005
    Consultant Contract Process NTP Issued 03/27/2006