Project Description:
ROYALSTON- BRIDGE REPLACEMENT, R-12-006, NORTH FITZWILLIAM ROAD OVER LAWRENCE BROOK
The proposed project consists of replacing the existing North Fitzwilliam Road bridge over the Lawrence Brook in its present location with minor improvements to the approach roadways. The bridge will be closed during construction.
Location:
  • Town of Royalston
  • Resident Engineer: Matthew Minihan
    Construction Contract Value: $1,313,437.00
    Construction Bid Price: $1,191,794.00
    Initial Construction Estimate: $1,187,696.00
    District: District 2

    Contracts (6) Progress
    # 37137 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/Replacement/Preservation Program. Final
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64324 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 69763 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 79598 -- Construction Contract
    Bridge Replacement (R-12-006) (Concrete) - North Fitzwilliam Road over Lawrence Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 07/26/2005
    Project Status Advertised 09/07/2013
    Project Management
    100% Design 100% Package Received 03/22/2013
    100% Design 100% Package Comments to DE 04/25/2013
    25% Design 25% Package Received 08/10/2009
    25% Design 25% Package Received 07/18/2012
    25% Design 25% Package Comments to DE 09/17/2012
    25% Design Design Public Hearing 01/10/2013
    75% Design 75% Package Received 03/22/2013
    75% Design 75% Package Comments to DE 04/25/2013
    Final Design PS&E Received 06/12/2013
    Final Design PS&E Received 08/27/2013
    Final Design PS&E to FAPRO 09/04/2013
    Consultant Contract Process Scope to DE 09/14/2005