MILFORD- UPPER CHARLES TRAIL CONSTRUCTION INCLUDES 2 BRIDGES: M-21-011 & M-21-026 (PHASE II)
Phase 2 of the proposed Upper Charles Trail consists of 2.9 paved-miles of bike trails that extend from Phase 1 at Deer Street to Hopkinton Town Line and from Friendly's parking lot at Veterans Memorial Drive to Holliston Town Line. Work also includes sidewalk construction, pavement marking and signing.
Location:
  • Town of Milford
  • Resident Engineer: Alan Webb
    Construction Contract Value: $3,335,630.00
    Construction Bid Price: $2,997,018.90
    Initial Construction Estimate: $3,531,187.33
    District: District 3

    Contracts (1) Progress
    # 58328 -- Construction Contract
    Construction of the Upper Charles Bike Trail, Phase2. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/02/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/29/2005
    Project Status Initiated 11/29/2005
    Project Status Advertised 12/27/2008
    Project Management
    100% Design 100% Package Received 08/18/2008
    100% Design 100% Package Comments to DE 12/10/2008
    25% Design 25% Package Received 01/02/2007
    25% Design 25% Package Comments to DE 04/11/2007
    25% Design Design Public Hearing 09/19/2007
    75% Design 75% Package Received 02/19/2008
    75% Design 75% Package Comments to DE 06/02/2008
    Final Design PS&E Received 12/23/2008
    Final Design PS&E to FAPRO 12/23/2008