| Project Description: |
MILFORD- UPPER CHARLES TRAIL CONSTRUCTION INCLUDES 2 BRIDGES: M-21-011 & M-21-026 (PHASE II)
Phase 2 of the proposed Upper Charles Trail consists of 2.9 paved-miles of bike trails that extend from Phase 1 at Deer Street to Hopkinton Town Line and from Friendly's parking lot at Veterans Memorial Drive to Holliston Town Line. Work also includes sidewalk construction, pavement marking and signing.
|
| Location: |
|
| Resident Engineer: | Alan Webb![]() |
| Construction Contract Value: | $3,335,630.00 |
| Construction Bid Price: | $2,997,018.90 |
| Initial Construction Estimate: | $3,531,187.33 |
| District: | District 3 |
|