Project Description:
ACTON- MAYNARD- ASSABET RIVER RAIL TRAIL CONSTRUCTION, INCLUDES BRIDGES, A-02-042 & M-10-012, A-02-034 & MPB WALL
Project Need: This Rail Trail project links the Assabet River National Wildlife refuge with the downtown Maynard business district and the South Acton Commuter Rail Station, providing an alternative transportation option. Project Description: The scope of work includes the construction of the Assabet River Rail Trail from the Stow/Maynard Town line to the MBTA station in Acton, a distance of 3.4 miles. The work will also include replacement of the existing Bridges at Tobin Park in Maynard, Mill Pond in Acton, and an approximately 200’ new boardwalk in Acton
Location:
  • Town of Acton
  • Town of Maynard
  • Resident Engineer: Patrick Marion
    Construction Bid Price: $6,719,972.00
    District: District 3

    Contracts (3) Progress
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 90722 -- Construction Contract
    Construction of the Assabet River Rail Trail and Boardwalk Including Bridges (Br. Nos. A-02-034, A-02-042 & M-10-012). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/27/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/17/2009
    Project Status Initiated 10/05/2006
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 08/03/2015
    100% Design 100% Package Comments to DE 09/09/2015
    25% Design 25% Package Received 11/09/2011
    25% Design 25% Package Received 10/21/2014
    25% Design 25% Package Comments to DE 01/06/2015
    25% Design 25% Package Comments to DE 06/04/2015
    25% Design Design Public Hearing 06/13/2013
    25% Design Design Public Hearing 04/30/2015
    75% Design 75% Package Received 10/21/2014
    75% Design 75% Package Received 04/17/2015
    75% Design 75% Package Comments to DE 06/19/2015
    Final Design PS&E Received 09/10/2015
    Final Design PS&E to FAPRO 09/15/2015