Project Description:
LOWELL- BRIDGE REPLACEMENT, L-15-045, MARKET STREET OVER THE WESTERN CANAL
The purpose of this project is to replace the bridge carrying Market Street over the Western Canal in the City of Lowell. The existing bridge, which was built in 1920, has a curb-to-curb width of 42.5 feet with two 9.5-foot sidewalks. The proposed bridge curb-to-curb width will remain the same. Market Street is a two-lane, two-way, urban minor arterial. Work on the roadway will include full depth reconstruction of 500 feet beyond the bridge on both approaches. Once beyond the limits of reconstruction, the pavement will be cold planed to match the existing pavement on the two approaches. A detour for vehicular and pedestrian traffic during the demolition, removal, and replacement of the existing bridge will be considered.
Location:
  • City of Lowell
  • Resident Engineer: Brian Noel
    Construction Bid Price: $2,392,000.69
    District: District 4

    Contracts (3) Progress
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 90708 -- Construction Contract
    Bridge Replacement Br. No. L-15-045 Market Street over the Western Canal. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/26/2016
    Contract Information
    Project Designer:
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/08/2005
    Project Status Initiated 08/03/2005
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 07/28/2015
    100% Design 100% Plans Complete 07/24/2015
    25% Design 25% Package Received 10/01/2012
    25% Design 25% Package Received 01/30/2015
    25% Design 25% Package Comments to DE 04/13/2015
    25% Design 25% Package Comments to DE 04/27/2015
    25% Design Design Public Hearing 03/17/2015
    25% Design 25% Plans Complete 07/24/2015
    75% Design 75% Package Received 10/01/2012
    75% Design 75% Package Received 01/30/2015
    75% Design 75% Package Comments to DE 04/08/2015
    75% Design 75% Plans Complete 07/24/2015
    Final Design PS&E Received 09/14/2015
    Final Design PS&E Received 02/25/2016
    Final Design PS&E to FAPRO 09/15/2015
    Final Design PS&E to FAPRO 03/01/2016