TEWKSBURY- RECONSTRUCTION OF RIVER ROAD, FROM THE TRULL BROOK TO THE ANDOVER T.L.
The project consists of widening River Road in Tewksbury from the Trull Brook crossing easterly 3600 feet to the Andover Town line. The proposed roadway cross section has a total width of 30 feet consisting of two 11 foot lanes and 4 foot shoulders. A sidewalk is proposed on the south side of River Road within the project limits. The project also includes full depth pavement construction, cold planning and overlay, roadway realignment, granite curbing, new drainage system, pavement markings, signing, minor landscaping and other incidental works. Right of way impacts are expected to be limited to temporary construction and permanent drainage easements.
Location:
  • Town of Tewksbury
  • Resident Engineer: Daniel Rychalsky
    Construction Contract Value: $4,412,896.00
    Construction Bid Price: $4,105,242.42
    Initial Construction Estimate: $5,020,316.00
    District: District 4

    Contracts (1) Progress
    # 66937 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of River Road and Merrimac Drive. (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/26/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 03/06/2006
    Project Status Initiated 08/03/2005
    Project Status Advertised 09/11/2010
    Project Management
    100% Design 100% Package Received 08/02/2010
    25% Design 25% Package Received 06/09/2006
    25% Design 25% Package Comments to DE 02/23/2007
    25% Design Design Public Hearing 11/07/2007
    75% Design 75% Package Received 02/19/2009
    75% Design 75% Package Comments to DE 06/01/2010
    Final Design PS&E to FAPRO 09/08/2010