Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NEWTON- WELLESLEY- WESTON- INTERSTATE MAINTENANCE ON I-95
Location:
  • City of Newton
  • Town of Wellesley
  • Town of Weston
  • Resident Engineer: Paul Pascucci
    Construction Contract Value: $21,695,321.80
    Construction Bid Price: $18,087,602.82
    Initial Construction Estimate: $15,915,991.50
    District: District 4

    Contracts (1) Progress
    # 54039 -- Construction Contract
    Work consists of safety and maintenance improvements along Route I-95 in Wellesley, Newton and Weston. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/28/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 09/27/2005
    Project Status Advertised 09/23/2006
    Project Status Advertised 01/12/2008
    Project Management
    75% Design 75% Package Received 06/29/2006
    Final Design PS&E Received 11/14/2007
    Final Design PS&E to FAPRO 11/15/2007