LYNNFIELD- PEABODY- INTERSTATE MAINTENANCE & RELATED WORK ON I-95
The project involves the resurfacing of both directions of I-95 in Lynnfield and Peabody. The project begins on I-95 at the Wakefield/Lynnfield townline and extends northerly to the Lynnfield Peabody town line. The project continues northerly into Peabody ending on I-95 after the Forest Street bridge and ending on Rt. 128 at the I-95 NB onramp in Peabody. The length of the project is 25,462-feet or 4.82 miles.
Location:
  • Town of Lynnfield
  • City of Peabody
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Albert Li
    Estimated Total Contract Cost: $9,008,047.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project