LYNNFIELD- PEABODY- INTERSTATE MAINTENANCE & RELATED WORK ON I-95
The project involves the resurfacing of both directions of I-95 in Lynnfield and Peabody. The project begins on I-95 at the Wakefield/Lynnfield townline and extends northerly to the Lynnfield Peabody town line. The project continues northerly into Peabody ending on I-95 after the Forest Street bridge and ending on Rt. 128 at the I-95 NB onramp in Peabody. The length of the project is 25,462-feet or 4.82 miles.
Location:
  • Town of Lynnfield
  • City of Peabody
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Albert Li
    Estimated Total Contract Cost: $9,008,047.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 05/17/2008 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/13/2007
    Project Initiation Form PRC Submitted 09/13/2007
    Project Review Committee PRC Approved 12/13/2007
    Project Status Advertised 05/17/2008
    Project Management
    Final Design PS&E Received 04/01/2008
    Final Design PS&E to FAPRO 04/22/2008