Project Description:
ADAMS- ROUNDABOUT CONSTRUCTION AT ROUTE 8 & FRIEND STREET
This project proposes to construct a roundabout with ADA compliant pedestrian accommodation at the 4-leg intersection of Route 8, Friend St and Renfrew St. The intersection is currently stop-sign controlled on the side streets. This section of Route 8 is on the National Highway System, but under municipal jurisdiction.
Location:
  • Town of Adams
  • Resident Engineer: Cathy Spaniol
    Construction Contract Value: $1,624,900.84
    Construction Bid Price: $1,438,636.00
    Initial Construction Estimate: $1,473,708.00
    District: District 1

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64325 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 84973 -- Construction Contract
    Roundabout Construction along Route 8 (Columbian Street) at Friend and Renfrew Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/28/2009
    Project Initiation Form PRC Submitted 08/10/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Status Advertised 09/13/2014
    Project Management
    100% Design 100% Package Received 04/25/2014
    100% Design 100% Package Comments to DE 05/19/2014
    25% Design 25% Package Received 09/27/2012
    25% Design 25% Package Comments to DE 11/07/2012
    25% Design Design Public Hearing 03/05/2013
    75% Design 75% Package Received 01/24/2014
    75% Design 75% Package Comments to DE 01/29/2014
    Final Design PS&E Received 08/01/2014
    Final Design PS&E to FAPRO 09/03/2014