Project Description:
HAVERHILL- MERRIMAC- AMESBURY- SALISBURY- INTERSTATE MAINTENANCE & RELATED WORK ON I-495
This I-495 Interstate Maintenance project consists of full width cold planing, furnishing and placing hot mix asphalt, placing permanent pavement markings, installing slotted reflectorized markers, and installing traffic data collection stations.
Location:
  • Town of Amesbury
  • City of Haverhill
  • Town of Merrimac
  • Town of Salisbury
  • Resident Engineer: Philip Jodoin
    Construction Contract Value: $14,860,745.00
    Construction Bid Price: $12,934,359.83
    Initial Construction Estimate: $12,549,027.00
    District: District 4

    Contracts (1) Progress
    # 58840 -- Construction Contract
    Resurfacing and Related Work on a Section of Interstate I-495. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/24/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2008
    Project Initiation Form PRC Submitted 03/07/2008
    Project Review Committee PRC Approved 06/12/2008
    Project Review Committee Letter 07/14/2008
    Project Status Advertised 04/04/2009
    Project Management
    100% Design 100% Package Received 03/04/2009
    100% Design 100% Package Comments to DE 03/10/2009
    100% Design 100% Plans Complete 03/20/2009
    25% Design 25% Package Received 06/11/2008
    75% Design 75% Package Received 01/09/2009
    75% Design 75% Package Comments to DE 01/26/2009
    Final Design PS&E Received 03/20/2009
    Final Design PS&E to FAPRO 03/23/2009