Project Description:
NORTON- BRIDGE REPLACEMENT, N-23-017, PLAIN STREET OVER THE CANOE RIVER
The purpose of this project is the replace the bridge carrying Plain Street over the Canoe River. The existing structure is a 21 foot corrugated pipe culvert which is now structurally deficient. The original culvert constructed in 1960 has a 24 feet curb to curb roadway width and one 6 feet sidewalk on the north side with a 5 feet utility pipe next to it. The out-to-out width of the existing culvert is 37.4 feet. It is anticipated that the structure will be replaced with a single span (spread prestressed concrete deck beam supestructure supported by integral abutments on H-piles) of approximately 36.5 feet. The proposed curb to curb width of the roadway over the bridge is 30 feet with a 5.5 feet sidewalk on the north side. The length of the project is 523.47 feet. The roadway is functionally classified as a local road. There will be minor roadway reconstruction and resurfacing work approaching the bridge.
Location:
  • Town of Norton
  • Resident Engineer: Amy Aveiro
    Construction Bid Price: $1,839,313.00
    District: District 5

    Contracts (4) Progress
    # 102485 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide road and bridge projects, for the purpose of mainta Final
    # 44056 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 90404 -- Construction Contract
    Bridge Replacement Br. No. N-23-017 (Concrete) Plain Street over the Canoe River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/28/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/02/2005
    Project Status Initiated 08/25/2005
    Project Status Advertised 08/29/2015
    Project Management
    100% Design 100% Package Received 07/15/2015
    25% Design 25% Package Received 01/22/2014
    25% Design 25% Package Comments to DE 03/31/2014
    25% Design 25% Package Comments to DE 06/23/2014
    25% Design Design Public Hearing 06/19/2014
    75% Design 75% Package Received 03/31/2015
    75% Design 75% Package Comments to DE 05/14/2015
    Final Design PS&E Received 07/15/2015
    Final Design PS&E to FAPRO 08/25/2015
    Consultant Contract Process Scope to DE 12/04/2009